Hi Experts,
This is my case:
1. I created a service purchase order - Quantity 1 UN - Price $3000
2. I created a Entry Sheet of this purchase order with Percentage quantity 50%
FM created the follow register:
Invoices 0100 Original $ 1500
Purchase Orders 0100 Original $ 3000
Purchase Orders 0200 Reduction $ -1500
Purchase Orders 0500 Adjustment by Follow-on Document $ -1500
The system releases all the committed budget with the operation 0500 Adjustment by Follow-on documente
This released budget could be consumed for other purchase orders. This is something unwanted.
How Can I do for solve this problem.
I show a image in: http://subefotos.com/ver/?e3e7c4d47a82f6001b6ff5babb18509bo.jpg[url]
Thanks in advance.
José Luis
Edited by: José Luis Rodríguez on Sep 9, 2010 7:09 PM
2010 Sep 09 7:08 PM
Hi Jose Luis
This behaviour normally has to do with your settings in terms of Units of Measure. If your UoM is set as 'Quantity-based', reductions are made based on quantities- See transaction CUNI.
If you switch to 'Value-based commitment update', you will achieve what you expect.
Have a look at this link too
[http://www.sdn.sap.com/irj/scn/weblogs?blog=/pub/wlg/18473] [original link is broken] [original link is broken] [original link is broken];
Hope this will help you
Kind regards
Mar
2010 Sep 09 7:08 PM
Hi Jose Luis
This behaviour normally has to do with your settings in terms of Units of Measure. If your UoM is set as 'Quantity-based', reductions are made based on quantities- See transaction CUNI.
If you switch to 'Value-based commitment update', you will achieve what you expect.
Have a look at this link too
[http://www.sdn.sap.com/irj/scn/weblogs?blog=/pub/wlg/18473] [original link is broken] [original link is broken] [original link is broken];
Hope this will help you
Kind regards
Mar
2010 Sep 09 11:51 PM
2014 May 22 7:46 AM
HI,
We are also facing the same issue, if you give some input how its resolve, it will be help for us.
2014 May 22 7:57 AM
Hi
I am also facing the same issue as mentioned below. Kindly guide me to resolve this issue.
it will be help for us.
This is my case:
1. I created a service purchase order - Quantity 1 UN - Price $3000
2. I created a Entry Sheet of this purchase order with Percentage quantity 50%
FM created the follow register:
Invoices 0100 Original $ 1500
Purchase Orders 0100 Original $ 3000
Purchase Orders 0200 Reduction $ -1500
Purchase Orders 0500 Adjustment by Follow-on Document $ -1500
The system releases all the committed budget with the operation 0500 Adjustment by Follow-on documente
This released budget could be consumed for other purchase orders. This is something unwanted.
How Can I do for solve this problem.
2014 Jun 03 12:49 PM
Hi Jeetendra,
Please go to SAP Netweaver-General Setting-Check Units of Measurement. (Tcode CUNI) Select your measurement what you have used in your PO. And tick the "Value based Commitment" there. It will resolve your problem.
Regards,
Ankit Agarwal