The project sponsor ultimately owns the output of the project so is responsible for its success; however it is unlikely that they have the technical knowledge held by the specialists in the team of a software development project. So somehow the Project manager will have to communicate the risks to them.
There are many ways to do this however the Sponsor should understand the risk management process that was
used to gather the risk to give them credibility and how they have been assessed and the actions and strategies to minimise those risks. The sponsor can then make the ultimate decision as to whether the project should continue. There may be huge risks that have a high likelihood and impact, but the sponsor may decide to continue even if you suggest that is not wise. It is ultimately their decision as the will carry the can for it if it fails (although you can guarantee that some of the flack will roll down to the PM).
It is also wise to note that Project Sponsors very often expect delivery to the original budgets and schedules despite risk and simply expect the Project manager to manage the risk out of the project. It is for this reason that the Project Sponsor should be kept fully up to date on a regular basis.
The risks should also be communicated to other key stakeholders in the business on a regular basis to ensure they are aware of how the risks are affecting the project. They may also be able to play a key role in risk management by reducing the risks.
Control the Risks
Simply identifying the risks and
assigning actions to people is not enough to manage the risks. To deliver risk management a risks register should be created to capture all detail about the risk including:
- Risk ID
- Description of the risk
- The impact if risk happens
- Likelihood (1-5)
- Any actions to reduce the risk
- Risk owner – the person whose area the risk affects
- Risk Actionee – the person best placed to perform the action to reduce the risk (usually different but sometimes the same as the Risk Owner.
- Risk Status – open, closed etc.
Risk updates should be a key part of any project meeting and actions should be tracked to ensure they have been completed properly. The status of the risk should also be monitored to see whether its likelihood or impact has increased or reduced. The project team meeting is also a good place to ask the team if there have been any new risks identified, if so these should be captured onto the risk register. A risk register is a live document and should be updated regularly rather than just filed away.
Learning the risks
When a project or stage has been completed a lessons learned review should be conducted to see whether the risks were reduced and managed effectively or whether there were issues with their risk management.
These lessons should then be captured and communicated throughout the project organisation. These lessons can then be used on other projects to aid their risk management and minimise their risks.
The lessons learned role is often performed by the Project Assurance function and captured into process and standard risk lists as a result of the Centre of Excellence function. The Project Assurance role would then ensure that new projects are made aware of the standard risks that may apply to new projects.
Summary
Risk is inherent to all projects particularly in fast moving environments like software development projects or development
phone tracker apps . This does not mean that you should avoid taking risks, as high risk projects often deliver high rewards. You should however ensure that you have identified the risks correctly and managed and communicated them to ensure their likelihood and impact has been reduced effectively.