We bill certain customer services upfront on a annual billing basis. These hours are use it or lose it basis for the billed period Example 20 hours billed for 01.01.2022 - 12.31.2022
These hours need to be tracked as consumed and any overage above 20 hours need to be billed at an agreed upon rate. Checking to see if anyone has come across the Same Billing solutions
we are on S4 Hana on premise 1809
2022 Jun 27 7:32 PM
Hi Ram - You could consider creating a project-specific pricing condition that uses a discount scale where a 100pct discount would apply up to the level of the hours provided for the fixed fee, beyond which a 0% discount would apply and normal T&E rates would be applied. This calculation would be specific to each Resource-Related Billing DMR and would work fine if you run RRB once at the end of the project to calculate the final bill.