2013 Dec 17 10:43 PM
Hello Gurus
I am new to SAP HR and trying to use Lean Staffing for scheduling employees to Projects.
- We have activated the below 4 Business Functions
PRS_ERP_CPILS_1
PRS_ERP_CPILS_2
PRS_GEN_UI
PRS_HCM_CPILS_1
- Later I added the below role to the Employee userid in SAP
SAP_SAWE_UNIVERSAL
Finally I assigned an employee to a Project using Staff Assignment.
Now I want to enter the Working Times for that employee against that Project.
However I am unable to see the Project in CAT2 in the Worklist tab.
Not sure how the functionality works, But Can you guys suggest me a way to enter the time sheets for the Project for which employees are assigned using Lean staffing ?
Thanks
Vinit
2013 Dec 18 12:19 PM
Hi Vinit,
Did you flag in the CATS Entry Profile in section Worklist: Lean Staffing?
( IMG-Cross Application Components - Time Sheet - Specific Settings for CATS regular - Record Working times - Set up data entry profiles- Section: Worklist: Lean Staffing).
Regards
Monika
2013 Dec 18 4:15 PM
Hi Monica
Yes .. The Data Entry Profile we are using is flagged for Lead Staffing in the WorkList section ...
Any more thoughts ?