Process Order detail scheduling picking the std values from Phase.

Former Member
0 Kudos
258

I'm working on an Implementation scenario, where the Master Recipe contains only one Operation and one phase. After the Process order is created the basic start and End dates remain same. I did check the formula in the resource(on testing its working fine). I did check the control key, formula parameters, scheduling parameters of the process order. I have maintained the std values in the phase appropriately.

Still the process order basic start/end dates are same, even though the process order quantity is of any quantity.

Request all to please provide some inputs.

Thanks,

Nil.

1 REPLY 1
Read only

0 Kudos
220

Sorry, this is not the right forum for technical questions - please log a note in OSS or contact SAP services. Thanks