Mass update Current Cost from Future Cost for all products

Ashali
Participant
0 Kudos
790

Hello,

 

I need to roll-up the Future (Planned Price), to Current (Standard Price) for all parts. Could you pls share the step required.

Thanks

Ashraf
S/4HANA Public cloud 2402

Ashali_0-1722280739103.png

 

 

1 ACCEPTED SOLUTION

Jessica_Dewald
Product and Topic Expert
Product and Topic Expert
707

Hello Ashraf,

To convert the costing results to current standard price, you need to mark and release your standard cost estimates.

See also here:

Marking and Releasing Standard Cost Estimates 

Price Update

Kind regards,

Jessica

View solution in original post

2 REPLIES 2

Jessica_Dewald
Product and Topic Expert
Product and Topic Expert
708

Hello Ashraf,

To convert the costing results to current standard price, you need to mark and release your standard cost estimates.

See also here:

Marking and Releasing Standard Cost Estimates 

Price Update

Kind regards,

Jessica

0 Kudos
668

Thanks!