2015 Aug 13 3:47 PM
Dear All,
Can we create partial billing in DBM Parts sale order?
If I processes post goods issue for partial items for those line items I have to create billing document. Can we create? (Like SD sales order)
Thanks in advance..
- Makarand
2015 Aug 14 6:40 AM
Hi Makarand Sir,
DBM do not have partial billing concept.. only way out is split billing, now it depends on customization of your parts order , 1.] Does it have split tab ? if your parts order does not show split tab configure the screen layout for that order type and rest will work fine. 2] I will suggest easy way out to copy service order type and use it for parts sales order,, many people are using this way ..but the non billed items will be considered fro WIP posting at month end, which should not be issue in your case.
Regards
Ganesh
2015 Aug 13 5:07 PM
Hi Makarand, Yes, we can create partial billing for partial goods issued in DBM JOb Order. The same can be handled through Create Billing Status. Regards, T.R.S.Praven
2015 Aug 13 9:51 PM
Hello Praveen,
Could you please elaborate your answer ? Please give me some details.
Thanks and Regards,
Makarand
2015 Aug 14 6:32 AM
Hi Makarand,
To enable partial billing for Partial goods issued you have to change the Goods movement statusID to partial in Billing_Create Action. Please find the screen shot below.
Once the same is done the partial billing can be done by puting the two items in two different jobs.
SPRO Path :- IMG-> Logistics Execution->Dealer Business Management->Order->Order control-> Define Action.
Hope this resolves your query.
Regards,
T.R.S.Praveen
2015 Aug 14 6:40 AM
Hi Makarand Sir,
DBM do not have partial billing concept.. only way out is split billing, now it depends on customization of your parts order , 1.] Does it have split tab ? if your parts order does not show split tab configure the screen layout for that order type and rest will work fine. 2] I will suggest easy way out to copy service order type and use it for parts sales order,, many people are using this way ..but the non billed items will be considered fro WIP posting at month end, which should not be issue in your case.
Regards
Ganesh
2015 Aug 14 8:55 AM
Dear Praveen and Ganesh,
Thanks a lot for your valuable inputs.
Ganesh your second option is a right solution for my requirement.
Thanks once again
- Makarand