Hello

Can anyone please advise where is that End time 24:00:00 is coming from ?

It only coming when i import operation using Tasklist.
But when adding operation manually on the same order then End time remain 00:00:00.

What change can i make to always have this as 00:00:00?

Accepted Solutions (0)

Answers (1)

Answers (1)

peter_atkin
Active Contributor

Aqva cool,

If its custom code, then check whether the first two fields are empty - then you can assume the time field is irrelevant.

NOTE: it also assigns the 24:00:00 in my S/4 2020 system when assigning a task list.

PeteA

former_member601006
Participant
0 Kudos

PeteA

If it's also happening for you then it seems it is a SAP standard to add 24:00:00.

In that case i will have to update the code.