on 2013 Oct 25 7:11 PM
Please could somewhone help me to understand:
- Why KOAR settlement is included in RPSCO table, but KOAO & KOAL are not?
Also, is there somewhere some description/documentation available on what is in principle included into RPSCO Table & wahts is not?
Many thanks in advance,
Daria
Request clarification before answering.
Hello Daria
this is all explain in note 51971
in short ..
settling from outside a project hierarchy to an element within the project hierarchy,
cost reporting for the project will therefore not show these settlement value.
I hope this helps
ger