on 2016 Feb 19 11:10 AM
Hi All,
I am configuring PPM 6.1.
In the config guide, we have an optional install for Business Package for SAP Portfolio and Project Management 5.0 73
1. What is the exact use of Business Package for SAP Portfolio and Project Management 5.0 73? What features does it enable?
2. How can we (functional) check whether this is installed in the client or do we need to ask basis ?
Regards,
Ashwini
Request clarification before answering.
Hi,
this is only needed in case you want to use PPM in SAP Enterprise Portal.
And it then has to be installed on SAP Enterprise Portal to provide portal role, menu, navigation etc. to users. See the Configuration Content for more details.
Kind regards,
Florian
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.