While creating project I want to Create a number activity under one WBS and under each activity i may have one or more services., since these activities are related to one particular division namely CIVIL Engineering. Similarly, i want to create for Mech Engg Department also. How to do.

Accepted Solutions (0)

Answers (1)

Answers (1)

Ken_Melching
Product and Topic Expert
Product and Topic Expert
0 Kudos

Under a Network Activity you can create Network Activity Elements. An Activity Element has all of the same functionality as an Activity with the exception of the scheduling functions. An element inherits the dates of its parent activity.

On an Activity and Activity element the main organizational object is the workcenter. You can create workcenters for the different engineering separtments.