Upon Process order creation, phases relationships are not according the master Recipe

PCSAPL3TX
Discoverer
0 Kudos
109

Hello fellow SAP Colleagues,

During some tests we found a strange behavior in Process orders, Upon creation from COR1 with backward in time scheduling, providing end date, Relationship Start to start between phases was not respected and instead a finish to finish one was adopted. Although if we press scheduling of order button it corrects the scheduling times to the correct start to start. 

When coming from a planned order this issue does not occur

 

Have anyone experienced this ? 

 

Thanks for Sharing

 

 