Upload new WBS'es to existing projects in PS

ansar_shaikh2
Contributor
0 Likes
652

Dear's.

We need to upload 3 additional WBS element to each of existing 800 project in SAP PS. All these project were created from RPM/cprojetcs link.

For newly created project we are able create addiotional 3 WBSEs for each of new item created in RPM. But client wants to update existing projects with 3 additional WBSEs.

Is there any upload program available or any other solution that can fulfill this one.

Thanks,

Ansar

Accepted Solutions (0)

Answers (2)

Answers (2)

kathy_belford
Explorer
0 Likes

Try using a LSMW with the t-Code CJ11, using an excel CSV or txt file enter in the project Def to assign the new WBS element to.

Depending on the settings in your system, you can use this to make multiple WBS Elements on level 1 in your project & then using the Edit>Object>Level Down to place the WBS Elements on the level you are needing them (i.e.: Level 3)

Former Member
0 Likes

Hi Ansar,

Seems you have to write z-program to do this if you do not want to create object link one by one.

Regards,

Alok.