on 2017 Oct 04 10:58 AM
Hi everyone,
I have a maintenance order whose operation 0010 contains a PR which didn't have a PO created and hence due to which i am unable to Technically complete the order. Also the
PR linked is not getting deleted via ME52n.
Can anyone suggest a SAP note to rectify this inconsistency.
thanks
Request clarification before answering.
Hello Nitin,
You can TECO order evenif PR exist .In your case i think you people made some restriction for this .
PM order PR can only be deleted via Work Order .
If PR has been released, first revoke release and then try to TECO order .It is standard , when work order TECO , Pr will get deletion flag automatically .