Hi everyone,
I have a maintenance order whose operation 0010 contains a PR which didn't have a PO created and hence due to which i am unable to Technically complete the order. Also the
PR linked is not getting deleted via ME52n.
Can anyone suggest a SAP note to rectify this inconsistency.
thanks
Request clarification before answering.
Nitin,
What is the full list of system and user statuses on this order?
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Nitin,
You can TECO order evenif PR exist .In your case i think you people made some restriction for this .
PM order PR can only be deleted via Work Order .
If PR has been released, first revoke release and then try to TECO order .It is standard , when work order TECO , Pr will get deletion flag automatically .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.