Unable to open decision Point in SAP PPM

Former Member
0 Kudos
423

Hi Experts.

I am working on PPM project., I set necessary configurations of decision points, when I create Item, I can see decision points in PPM, but when I click on any decision point, nothing happens, As per my knowledge, it should open and I should be able to change the status of particular decision point and thereby I can move to next decision point. But in my portal, nothing happens on click of decision point.

PPM version Is 6.1

Please assist me in this regard

Regards

Gaurav

View Entire Topic
Former Member
0 Kudos

Dear Judith,

Many Thanks ! These issue is resolved. Decision Point Navigation Service was not activated properly
Please help me in below queries.

1. My scenario has below requirements.

a) I am transferring Budget from PS to PPM, Facing this Warning -

No link exists between SAP PS Project element and selected SAP PPM items, Any Inputs ?

b) Is it possible to transfer Budget from Portfolio Item ( Yearly) at PS Project Definition Level (Level) ??

c) Do we have standard checklist at Portfolio Item Level similar to Checklist in C-projects ??
If our requirements is to have checklist completion as mandatory criteria to approve Decision point status in item, Do we have any standard solution in this regard ??


d) I am transferring Project from Portfolio Item to SAP PS (Map Item Type to PS project) , which status are possible in standard to synchronize between PPM & PS.
I.e.
My Understanding
Item (PPM) <--> Project (PS)
Can I Release my Project through Item Status Release?
Can I TECO my PS Project through Item Complete?
Can I Close my PS project through Item Close?
Which scenario is possible in standard.?

e) Currently we are designing solution through portfolio item to PS project (Automation), But confused whether C-projects should be used for Project Transfer from PPM to PS ?
Our client is oil & gas, they need little bigger structure, they need flexibility in adding wbs, network, activities
Can network/activities be transferred from C-project to PS in standard ??

Apologies, Have added so many basic queries 🙂