on 2011 Feb 18 9:23 AM
Hello,
I have one scenario, where we have created work area. We have used integration object of work area and have linked it with SAP-PP object work center. We are able to go to the work centere screen directly from work area.
But client wants it other way round. They want to access the work area from the work center screen using the tcode: CR02 / 03.
On work centere screen I could not find any option to go to work area to which this work center is linked.
Is there any option using any BAdI or user exit to provide this two way linking between work area in EHS and work center in PP?
Regards,
Niraj
Request clarification before answering.
Hi, Its not possible to map in standard, but may be you can explore the possibilities of changing at Program level or Enhance existing screens by adding work area object in work center screens.
But my advice is not to change the standard programs for this kind of requirements.
Regards,
Keshav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
15 | |
2 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.