on 2020 Jul 22 7:01 AM
Hi All,
The Transfer to CO only appears to be working for methods updating using FPCA (or Plan Cost). The methods which use key figures for ETC or EAC are simply not updating ECP but there are no error messages.
When we are running the Mass Forecast program /CPD/PFP_MASS_FORCAST_TRANSFER:A message appears stating the Transfer process initiated.
On checking the SLG1 log
Transfer process initiated
0TRANS_WBS_EAC_FORECAST: WBS XXXXXXX EAC transferred
Transfer process completed.
But when we check ECP values in CJ20N we get no values have flowed in. Neither there is data in the Infocube.
Regards,
Suman Misra