Total plan costs where from in repair service

JoneZL
Participant
0 Kudos
190

Hi,

The total actual cost will be what is posted to the service order. I do not know how total planned cost on service order is populated/updated, could you help me, thanks.

Accepted Solutions (0)

Answers (1)

Answers (1)

peter_atkin
Active Contributor
0 Kudos

Jone Zhang,

The planned costs are derived from the information entered into the operations. So it looks like you have planned some services on one Cost Element /GL and you have created the actuals on another Cost Element /GL.

If you dig into the operation for these services you should see a Cost Element /GL assignment.

PeteA