To bring HR work centers in capacity and utilization reports

former_member601834
Discoverer
0 Kudos
286

We are using HR work centers as RP nodes for planning in MRS. But we are not getting HR work centers displayed in /MRSS/UTILREP and /MRSS/CAPACITY_REP reports.

Is there any way to use these reports for HR work centers?

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member529748
Discoverer
0 Kudos

Capacity report and Utilization reports as standard are not meant for HR work centers.

But you can explore maintaining HR work center node for scenario 'VERIMULT' in below customizing path.

SPRO ->Personnel Management->Organizational Management->Hierarchy Framework->Object Manager->Define your own scenario.

See if this helps/works for you.