Time-based maintenance package

combatraccon
Explorer
0 Kudos
256

Hello/ Referring to the previous plan, we have set 7200 hours per year. We would like to have it settled to 8766. Given that, What should be the cycle length for a month or quarter? Cause there are the 28-day months and the 31-day months

Accepted Solutions (0)

Answers (1)

Answers (1)

Oscar_DC
Active Contributor
0 Kudos

I'm not sure I completely understand your question - but I can tell you that SAP considers a month to ALWAYS have 30 days. As a side note for other folks - if you're using "Time-key date", do not use the date after the 28th or you'll see some inconsistencies.