on 2012 Aug 26 2:56 AM
Hi all,
We create a item and integration with PS at PPM 5.0.When the PS project actually incurred costs 777, we execute RPM_FICO_DATA_TRANSFER in the SAP ERP system,the cost was transfered to the item ,but the second costs 123 we execute RPM_FICO_DATA_TRANSFER it's show an warning "Start data missing for item...",the costs 123 add to the table RPM_FIDATA was success,but the finalcial planing of item only show the costs 777.Pls see attchment for detail.
Pls help us.Thank you.
Request clarification before answering.
Hi Qiao,
1) the warning has nothing to do with the actuals. It is related to the budget (value type 41)
2) I do not see the value 123 in your screenshot. Is it really there?
3) have you used settlement in ERP?
4) have you tried to run /RPM/FICO_INT_PLANNING again?
Bets regards
Thorsten
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.