Task status report in cProject 3.1

former_member845166
Active Participant
0 Kudos
218

Hi,

I want to extract task status report from cProject 3.1.

Report should contain task name, status, start date,end date , effort etc.

Thanks in advance

Shiv

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Activate the form DPR_TASK_HIER for a particular Project type in SPRO screen. Now keep the cursor on any task in cProjects & click on Print pushbutton, this will generate a PDF Report which will contain Task name, Constraint dates, actual dates, administration details etc. In order to add more data to the Report, goto transaction SAMRTFORMS & edit the form DPR_TASK_HIER.

Hope this will help you.

Regards,

Sujay G

Answers (0)