on 2007 Apr 23 10:48 AM
Hi,
I want to extract task status report from cProject 3.1.
Report should contain task name, status, start date,end date , effort etc.
Thanks in advance
Shiv
Request clarification before answering.
Hi,
Activate the form DPR_TASK_HIER for a particular Project type in SPRO screen. Now keep the cursor on any task in cProjects & click on Print pushbutton, this will generate a PDF Report which will contain Task name, Constraint dates, actual dates, administration details etc. In order to add more data to the Report, goto transaction SAMRTFORMS & edit the form DPR_TASK_HIER.
Hope this will help you.
Regards,
Sujay G