Table for estimated planned cost of project in PPM

Former Member

Accepted Solutions (1)

Accepted Solutions (1)

judith_gabriel
Product and Topic Expert
Product and Topic Expert
0 Kudos

Dear Chandan,

are you talking about the "costs" which are displayed by the "financial integration" on tab "accounting"?
When "yes" - the values are available in the ERP-system where the PS-project or Internal Order
(or Easy Cost Planning) are available.
You can use transaction RKACSHOW for the corresponding wbs-element,... to receive the tables
with the datas. (Easy cost planning datas are stored in tables CKHS, CKIS,

Best regards,

Judith

Former Member
0 Kudos

Dear Judith,

Thanks for reply.

in my scenario Planned cost is on Portfolio Item level, Path : Portfolio Items >> item > Financial  & Capacity planning >> Financial Planning >> Planned cost.

For this planned cost, Resource cost taking automatically from assigned resource & Other cost like material, expenses etc. we are entering manually..

so for this planned cost i m finding tables.  please help.

Thanks & Regards

Chandan

Former Member
0 Kudos

Hello Chandan

Have you checked the /rpm/fin_plan table yet?

Can you get to this table as follows:

From /rpm/item_d get the Item GUID field. Then you can input this field value in the PARENT_GUID of table /rpm/fin_CAT. Here you will copy the relevant GUID (for the category you want)

Then you can input this field value into the PARENT_GUID of table /rpm/fin_group. Here you will copy the relevant GUID (for the group that you want)

Now you can input this last GUID into the GUID of the /rpm/fin_plan table. You will now see all of the configured financial views as well as the values

Hope this helps

With regards

Chatsworth

PS: Any financial values aggregated/Rolled Up for Integrated  Fnancial views (such as Actual or Commitment from PS project linked to Item) can be found in table RPM_FIDATA.

Former Member
0 Kudos

Hello Chandan

Have you checked the /rpm/fin_plan table yet?

Can you get to this table as follows:

From /rpm/item_d get the Item GUID field. Then you can input this field value in the PARENT_GUID of table /rpm/fin_CAT. Here you will copy the relevant GUID (for the category you want)

Then you can input this field value into the PARENT_GUID of table /rpm/fin_group. Here you will copy the relevant GUID (for the group that you want)

Now you can input this last GUID into the GUID of the /rpm/fin_plan table. You will now see all of the configured financial views as well as the values

Hope this helps

With regards

Chatsworth

PS: Any financial values aggregated/Rolled Up for Integrated  Fnancial views (such as Actual or Commitment from PS project linked to Item) can be found in table RPM_FIDATA.

Former Member
0 Kudos

Thank You very much Chatsworth,

I got it.... Thank you for your solution.

Thanks & Regards,

Chandan

Former Member
0 Kudos

Hi Chandan

Please mark the post as complete if your issue is resolved

Thanks

C

Former Member
0 Kudos

Dear Chatsworth,

Please help me  to find the table for portfolio Item No. Description.

please help..

Thanks & Rgds,

Chandan

priyatham_kasu2
Active Participant
0 Kudos

Hi Chandan,

CGPL_TEXT is the table where PPM Objects description gets saved.

Regards,

Priyatham