Hello everyone,
I'm with difficult for make works the sync status from SAP PS (Project Definition - System Status) for Portfolio Item. Is this possible right?
I have configured in SAP Portfolio and Project Management > Common Functions > Decision Flow Management Settings
a) Check and Maintain Settings for DFM;
b) Define DFM Objects Link Types;
c) Maintain Objects from Synchronization;
d) Define Execution Mode for Synchronization of Objects;
e) Define customer -specific execution mode for syncronization;
SAP Portfolio and Project Management > Common Functions > Status Synchronization
I want to show the system status from SAP PS (Project System) for the portfolio item. Not in decision point, and yes in portfolio item. Is it necessary create a field first? How works?
Here are some screen shots about the configuration.
Thank you so much.
Regards,
Lilian Amélia Pereira
Request clarification before answering.
Dear Lilian,
you have to use the one of the BAdIs (like BADI_CPPM_RPM_PS_SYNC_WBS) of enhancement spot ES_BADI_CPPM_RPM_PS_SYNC to trigger the DFM synchronization from ERP-system to PPM-system.
Best regards,
Judith
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
6 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.