on 2006 Oct 30 5:36 AM
Dear all,
I am new to CProjects and currently working on migrating legacy data to CProjects through XML. I am facing some strange problems when migrating project data with multiple phases. If the project already exists in Cprojects, the XML import transaction hangs indefinitely and a timeout exception is thrown. While on the other hand, if I upload a new project (with same set of phases), it is readily imported without any problems.
Kindly help!
Thank you all!
Request clarification before answering.
Hi Vivek,
If the project already exists, the system creates a simulation from the imported data. You then need to move the simulation to your operational project by performing a reconcilliation. You can't simply overwrite an operational project via an import.
I have included some links below from SAP help which may help (cProjects 3.1).
http://help.sap.com/saphelp_cpro31/helpdata/en/26/cb8740f8aacf62e10000000a155106/content.htm
http://help.sap.com/saphelp_cpro31/helpdata/en/b0/d562404fb6cd01e10000000a155106/content.htm
Regards,
Lashan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Lashan,
Thats what the problem is! The import operation never completes, since it hangs indefinitely. Reconciliation can be done only if the import operation succeedes - which is not the case with me.
Regards,
Vivek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check, that you can not migrate complete folder in cProject. Its SAP have limitation on that so if this the case, go one by one file in sequence.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.