on 2024 Oct 23 4:12 PM
Hi Experts, I'm trying to achieve the automatic closure of PPM Portfolio Item from PS Project Defin. for System Status - CLSD. I have done the following steps:
| Source Grouping: | PD | Project Definition (PS) |
| Target Grouping: | PPO | Portfolio Item (Portfolio Management) |
| DFM Business Transaction: | Complete | DFM3 |
2. MAP PROJECT / INITIATIVE BUSINESS TRANSACTION TO DFM BUSINESS TRANSACTION
| Source Grouping: | PD | Project Definition (PS) |
| Target Grouping: | PPO | Portfolio Item (Portfolio Management) |
| Source Business Transaction | Complete | BABS |
| DFM Business Transaction | Complete | DFM3 |
3. MAP DFM BUSINESS TRANSACTION TO PORTFOLIO MANAGEMENT STATUS
| Source Grouping: | PD | Project Definition (PS) |
| Target Grouping: | PPO | Portfolio Item (Portfolio Management) |
| DFM Business Transaction | Complete | DFM3 |
| Portf. Mgmt Status | Z0003 | Closed |
The BADI is active BADI_CPPM_RPM_PS_SYNC_PROJ
Also we have done all config mentioned in -
Maintain Objects for Synchronization , Maintain Attributes for Synchronization Scenarios and Integration with Other SAP Components > SAP Portfolio and Project Management > Portfolio Management > Maintain Gen. Settings for Portf. and Proj. Mgmt Intgrn
Still we are not able to achieve the automatic closure
Would really appreciate any support or config steps I missed.