Start/End dates for cProjects

former_member1042016
Participant
0 Likes
140

Hi,

While creating a Project in PS, if the Start/ End date of the project is a weekend or holiday, the start of the cProject shifts to a working day u2013 is there a config to set this to take the actual date (working or holiday). Waiting for your reply @ earliest.

Thanks & Regards,

Gaurav

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member1042016
Participant
0 Likes

Purpose not solved

thomas_berndt
Advisor
Advisor
0 Likes

Hi Gaurav,

this shifting of the dates is likely a "feature" of the scheduling process. As soon as a calendar has been maintained for the objects the weekends are taken into account and the dates determined for the object being subject of scheduling and it is enforced that the dates are working days.

To answer your question, if you maintained a calendar without weekends and public holidays - or no calendar at all - this shift won't occur.

Hoping this helps...

Best regards,

Thomas