SM36 - Job schedule - how to set job dependency

0 Kudos
551

Hi,

Job 1 - start run at 5 pm

Job 2 - start run at 10 pm ONLY IF Job 1 has completed successfully. Else do not start run.

How do I set this hard dependency using standard SM36?

'After job' starts the Job 2 immediately when the Job 1 finishes. As I have mentioned above, Job 2 should start at a later time, but should check the Job 1 status before running. How to achieve this without development?

Accepted Solutions (0)

Answers (1)

Answers (1)

priteshkumar
Participant
0 Kudos

Dear Sankaralingam,

I am not aware about standard solution for your requirement. But In case if you have access to solman you can take help from ABAP to understand logic of below program.

Thanks,

Pritesh Kumar