Scheduling factory calendar issue.

kjashwan
Explorer
0 Kudos
513

Scheduling Backward scheduling
Planning strategy :- 10
Factory calendar :- 5 working days

Problem :-
As per the factory calendar, Saturday and Sunday's are non working day.
In the production order, during scheduling, if the start day of production lies on the weekends, the system proposes the previous working day, i.e. Friday. The user's expectation is that the system needs to propose the successive working day after the weekends, i.e. Monday.
Please do advise , how could we achieve this result.
Thanks in advance.

View Entire Topic
kjashwan
Explorer
0 Kudos

Dear Experts

Waiting for the advise

Thanks and regards