on ‎2010 Jun 15 2:35 PM
Dear,
Could somebody please tell me in which table I can find the earliest scheduled start and finish dates for the PHASE of cProjects?
thanks!!!!
grtz,
b
Request clarification before answering.
Hi Bert,
Please have a look to CGPL_PROJECT.
Matthias
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thx Matthias,
this table indeed gives me the phase details;
but, where can I found the link between the phases and the project?
Is it table CGPL_HIERARCHY? however how do make the distinction between the different project elements (phases, tasks,etc)?
..am a bit confused with the external number, GUI ID, CGPL ID...
rgds,
bert
Hi,
That's right, you can get the links in CGPL_HIERARCHY.
In CGPL_PROJECT, you can filter on object type to know which project element it is, for instance:
- DPT: project definition in teamplate,
- DPO: project definition in operational project
- PPT: phase in template
- PPO: phase in operartional project
- ...
Matthias