If WBS element is in TECO status.

And it's network and activity is REL status but still user able to execute and fill data in activity.

However WBS element TECO status and other it's network and activity REL also user should not execute data.

Any configuration which I need to do to stop when WBS element is in TECO and other network and activity is in RELEASED user should not execute any data in cj20n t code

Accepted Solutions (0)

Answers (1)

Answers (1)

Ken_Melching
Product and Topic Expert
Product and Topic Expert
0 Kudos

You need to set the NWA status to TECO as well.  REL is the "open for business" status, it restricts very little.