SAP PS conversion project.

Anmol_Singh12
Explorer
0 Kudos
277

Hi all, I am working in SAP conversion project from ecc to hana and I am leading SAP PS. Can you please help with all the activities which are done in SAP Project systems in conversion project.

Regards

Accepted Solutions (0)

Answers (1)

Answers (1)

JLEPM
Discoverer
0 Kudos

Hi, ok, then without knowing which kind of organization or Company you are working with some thoughts. Because you are doing conversion, I assume that PS-module have been used already, some cases even decades... Most probably there are customizations e.g. specific Z-reports. Have you already done fit-gap analyses (ECC/PS vs S/4HANA EPPM/CPM/PM)? What actually would be needed? Are standard (existing) features enough? Depending e.g. how much new CloudAPAB will be needed, impacts costs and time, also migrations, tests, change management, etc., etc.