2024 Mar 31 12:39 PM - edited 2024 Mar 31 3:02 PM
Hello everyone,
In SAP Project System, in transaction CJ20N, when I assign a material component to an internal activity and choose my material, then I select "L" stock item for this material and I choose the following procurement type to generate a PR: PReq + Reservation for WBS Element. Afterwards, I enter the requirement quantity for this material component and then I hit enter on the keyboard to finalize the creation of this material component. I realize that the GL account assigned to this material automatically changes, from 3090300 (GBB-->VBR) to 1211000 (BSX) and an error is shown which says "GL account 1211000 is invalid". I can't save the progress for my project because when I do there is error in calculating costs since the system saw an error in this material component. What could be the cause of that?
Note: My project stock is maintained as valuated stock in the project profile configuration.
Thank you
Request clarification before answering.
With Valuated Project Stock at GR of the PO it will post to a Balance Sheet Inventory Account (they typically start with a 1). So that looks correct. What error message (and error message number) are you getting?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Sir,
The error description is as follows:
Message No. CO860
The G/L account that you have entered is invalid.