Hi

I have a Scenario where an Item passes through some Decision Points Like Gate 1 -> Gate 2 -> Gate 3 -> Gate 4

After completing Gate 1 & Gate 2, at the time of Gate 3 Decision Point i need to trigger a backward movement as an exceptional case i.e from Gate 3 -> Gate 2 -> Gate 1 and once the activity pertaining to Gate 1 is completed then based on the status it will again follow the same sequence of decision points i.e Gate 1 -> Gate 2 -> Gate 3 -> Gate -> 4.

Accepted Solutions (1)

Accepted Solutions (1)

judith_gabriel
Product and Topic Expert
Product and Topic Expert
0 Kudos

Dear Simon,
You can use the functionality "Revert to previous decision point" on Gate 3 to activate Gate 2 again.



Best regards,
Judith