on 2022 Sep 15 9:40 AM
Dear community,
is there any chance to lock plan data (e. g. duration, start, finish, etc.) as soon as the project/phase/task status is set to 'Released'? In case of a necessary change, a higher autorithy must approve any actions.
Example:
The Project Managers management agrees to a specific project timeline. The system status of the PPM-Project will be set to released. To prevent any changes without approval, we´d like to lock the time line specific information.
Is there a function like this in PPM standard?
Thank you very much!
Warm Regards,
Daniel
Help others by sharing your knowledge.
AnswerRequest clarification before answering.
Create a User Status Profile that is valid for Phases and Tasks and control the business processes with it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
3 | |
3 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.