SAP PPM in the tasks . dont have the "create subproject" button

Accepted Solutions (0)

Answers (1)

Answers (1)

judith_gabriel
Product and Topic Expert
Product and Topic Expert
0 Kudos

Dear Zhao,

You can select the task in the main-project and on tab "Basic Data" you can find the field "Subproject Number" where the subproject can be assigned.



Best regards,
Judith

0 Kudos

sorry, it is not my means. I want to know how to display the button. now I have ticked the subproject in the configuration, and I am already the biggest permission. but i still cant find the button.please help me.

ravi_ekambaram
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Zhao,

Are you trying to find 'Create Sub project' button in top menu where create buttons are there? If so, such kind of button is not delivered as standard by SAP. Instead you have to first create a sub-project in similar way as creating new project(lets assume it as XYZ). And then go to Main project(ABC) task A & then to 'General' tab where you have an field for selecting the sub-project. Click on selection options in that field and search for the sub-project(XYZ) which you created. Once you save, these above projects are part of multi-project management, where you have Main project & sub project for a task.

Hope this clarifies your question.

Regards,

Ravi