on 2017 Sep 28 1:12 AM
Hi,
I am on PPM1.0 on Hana 1610 on Premise version. PPM is installed on the same box as PS.
1. I have done the Financial Settings in Base System interface and linked the Value type 4 with Cost elements.
2. I have linked PS Project, WBS with PPM item in Object Link.
3. When I execute RPM_FICO_DATA_TRANSFER and it sucessfully transferred. no error or warning
4. I check table RPM_FIDATA and the data exists.
However, I dont see the Financial planning screen updated in PPM.
Can someone help, what went wrong?
Thanks
Anjali
Request clarification before answering.
Hi Anjali,
Apart from Judith's solution, check this also if it helps.
https://launchpad.support.sap.com/#/notes/2556351
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Anjali,
Start report /RPM/FICO_INT_PLANNING with the selection "planning, rollup" for the item. Then the datas should be transferred from table RPM_FIDATA to table /RPM/FIN_PLAN.
Best regards,
Judith
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
6 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.