Hi,

I am on PPM1.0 on Hana 1610 on Premise version. PPM is installed on the same box as PS.

1. I have done the Financial Settings in Base System interface and linked the Value type 4 with Cost elements.

2. I have linked PS Project, WBS with PPM item in Object Link.

3. When I execute RPM_FICO_DATA_TRANSFER and it sucessfully transferred. no error or warning

4. I check table RPM_FIDATA and the data exists.

However, I dont see the Financial planning screen updated in PPM.

Can someone help, what went wrong?

Thanks

Anjali

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member301510
Contributor
0 Kudos

Hi Anjali,

Apart from Judith's solution, check this also if it helps.

https://launchpad.support.sap.com/#/notes/2556351

Regards,

former_member301510
Contributor
judith_gabriel
Product and Topic Expert
Product and Topic Expert
0 Kudos

Dear Anjali,

Start report /RPM/FICO_INT_PLANNING with the selection "planning, rollup" for the item. Then the datas should be transferred from table RPM_FIDATA to table /RPM/FIN_PLAN.


Best regards,
Judith