SAP PPM 6.1 Task Severity not working

former_member185558
Active Participant
0 Kudos
291

Hello,

For my Project Type , I have settings as

I went to Evaluations, and clicked Create Evaluation, enterred my Project and clicked on current data,

Still Severity is shown as No Value set for all tasks and Project defn.

I gave a try by runnign program DPR_EVE_BATCH_DPO for this project but still no change.

Please help , suggest what am I missing.

Thanks and regards,

Niketan

Accepted Solutions (0)

Answers (0)