on 2015 Jun 03 3:05 PM
Hello experts,
I have configured in PPM the cost planning in PS version 0 , this is working. The users can see the cost planned in PS in SAP PPM.
Is it possible update a cost plan with version different of 0 for PPM? How?
Anybody have a specific documentation about this?
Best regards,
Lilian Amélia
Request clarification before answering.
Hi Lillian,
I found this text in page 113 of the PPM Configuration guide:
"Define financial views for budget or planned cost transfer in the Customizing for SAP Portfolio and Project Management under -> Portfolio Management > Global Customizing > Portfolio-Independent Settings >Define Financial and Capacity Views
If you have set a view in the Amount Type for Transfer column to Planned Cost Transfer, you have to select a CO Version which is used in the data transfer."
SAP Note 1826389 - PPM 6.0: Configuration Content
Hope it helps!
Best,
Fernando
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Lilian,
the CO Version can be maintained in customizing of "Define Financial View".
Best regards,
Judith
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.