on 2023 Feb 13 11:49 AM
Hi,
I have an issue with PM integration with SAP MRS. I am doing MRS configuration on MRS V 10.
Initially when I configured the system, demands were showing. But now when creating a new work order in PM order, it is not updating in SAP MRS planning board. I have checked demand table /MRSS/D_DEM_H table, orders entry not available. Can anyone please let me know what configuration I am missing here.
I am attaching all the screenshots.
Old demands reflecting in planning board.
Order Integration maintained.
Resource planning relevance Indicator is set.
Control Integration PM/CS
Work Center category is also 0005 (Plant Maintenance). Let me know if I am missing any key configuration.
Will appreciate with points.
Request clarification before answering.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.