on 2019 Feb 28 9:47 AM
Hello experts ,
We have weird issue related to IA02-IA03 transaction code which we use to define maintainance package for equipment plan.
We choose any strategy regarding to maintainance package for any equipment plan .But when we try to create work order for this maintainance which we have planned before it is giving error like "there is no maintainance package for this ...." .We are sure about that we have defined maintainance package for this equipment plan but weirdly it has gone by itself and we can not see anymore.
I am not PM expert so you may find the question silly but I am just trying to figure out what is going on and help to other colleagues.
Any help or comment will be appreciated .
Thank you .
Here is the screenshots :
Request clarification before answering.
In the task list (IA02/3), there is a menu path for something like "Object Overview" and this will give you a graphical overview of the whole task list including packages assigned to each operation.
See if this highlights any issues.
Also, can you send the error message number and text please.
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
3 | |
3 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.