SAP MRS time allocation unit (hours, days) not changeable

emanuel_gampp
Explorer
0 Kudos
423

Hello,

I have actually two questions:

- is there a chance to change in MRS the duration unit in "time allocations"? With our settings I can see the different units but they can't be changed:0

- for normal assignments we have selected "day based scheduling" with 8 working hours. Is it possible to select for time allocations also 8 hours if the unit days is chosen?

Accepted Solutions (1)

Accepted Solutions (1)

mohammedyakub_shah
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Time allocations are actually time streams which are repeated in nature or only single occurrence similar to HR work schedule where you can have one day / part day absence or a sequence of available time. That is the design for time allocations.

But assignments are also capacitive in nature where they can run for months at a time, therefore they have a bigger definition of unit. I am sorry to state you cannot change the unit for TA's.

Thanks and Regards,

Mohammed.