SAP DM: Change between OEE reason codes which belong to the same time element time

DaMa
Explorer
0 Kudos
317

I have set up different time elements and assigned them to the time element types. I also defined OEE reason codes and assigned them to the time elements. But now I have the issue that when I change a ressource from one OEE reason code to another one which belongs to the same time element type, the system doesn`t update the reason code. It remains with the original OEE reason code.

When i change to an OEE reason code which belongs to a different time element type, it works well. 

Do I miss any setting for that?

I am using an Order POD. To change the OEE reason code I am using the "ressource status with reason code Plugin".

Accepted Solutions (1)

Accepted Solutions (1)

harry_lube
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello,

thank you for addressing the issue. It is a known gap which is planned to be closed in one of the next releases. A change of reason code is not supported unless the status of the resource is changed as well.

Best regards, Harry

 