hi everyone,

Anyone here who majors in Project System of S/HANA。I can't transfer the schedule dates of the activities to the WBS element to which they are assigned when I carry WBS scheduling,see as the follows:

I have tried all the way I can find,but failed.Is there any workaround?

Thx.

Accepted Solutions (0)

Answers (2)

Answers (2)

kenmelching
Active Contributor
0 Kudos

We had the same problem, this is what SAP said in our incident which worked.

Please perform the manual steps as per the Note below:

Note 2652944 - CJ20N: scheduling function does not work with note 2417395 - ii

After which please implement the code correction from the Note below:

Note 2498090 - CJ20N: scheduling function does not work with note 2417395.

akashkhandelwal368
Active Participant
0 Kudos

Hi,