on 2019 Jun 13 7:01 AM
Hi All,
My customer wants to add new fields to Risk Management views in SAP CPM 2.0.
Do you know if the BAdI Processing Risk Events can be used for that?
Is there any other possible solution for this requirement?
Thanks
Request clarification before answering.
Risks in CPM are built on IAM just like the Issues and Change Requests on PICM. You will need to enhance the business object. Look at BOBF under Business Process Objects for /IAM/ISSUE and /IAM/ACTIVITY. There is a sub-object /CPD/ISSUE_ENH_RM for enhancing risk management.