on 2023 Jul 09 10:19 AM
Hi,
Is it possible for the system to compute revenue recogntion using key EPMFC ( cost based POC) for project with billing element at the top with plan revenue, and all the plan costs and actual cost are at separate lower WBS elements. This is becuase the client need to group and analyse cost by phases.
Appreciate your help.
Thanks
Request clarification before answering.
Yes, absolutely, this is the SAP standard behavior. Rev Rec will be calculated at the WBS that is assigned to the Sales Order Item. The plan and actual costs will be aggregated from all of the lower level WBS elements.