on 2021 Feb 21 1:26 PM
Hi,
We have configured the Resource Type and assigned Resources in the configuration under SAP Commercial Project Management > Project Cost and Revenue Planning.
Checked and assigned Resources Type to the Plan Scenario.
However when we are trying to plan in the Monthly Planning Workbook for the Baseline Version the Resource Type could be selected but the assigned Resources are not coming up in the Analysis for Office.
Regards
Suman Misra
Help others by sharing your knowledge.
AnswerRequest clarification before answering.
There were some discrepancy in the Configuration of Resource Types and for those Resource Types where the issue were had Blank Value in the Selection Criteria. Example shown in the screen shot.
This was identified by the BW-IP team and later after deleting the field name with Blank Field Values the issue was solved and hence I am closing this thread.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.