Questions on EH&S Specification

Former Member
0 Likes
633

Hello All,

I have two questions

1.when I go to CG02 transaction to change a specification, somehow the Change Number field is greyed out. I am not able to make any changes using Engineering Change. How to correct this, so I can change specifications (real_sub) using change masters ?

2. Also I can link material master from specification. Basically from inside the view of specification I can see Material Master linked to it. Can I do the reverse, somehow from inside Material master can I see the specifications assigned to it ?.

Thanks,

Sachin

View Entire Topic
Former Member
0 Likes

Hello,

Can someone please guide as how to configure screen 91 in Material Master.

Thanks,

Sachin

Former Member
0 Likes

Hello Sachin,

Navigate to Logistics General and access Material Master in SPRO.

Under Configuring the Material Master -> Define Structure of Data Screens for Each Screen Sequence, check whether the screen sequence SP exists. Also check whether screen 91 exists in SP and whether it has the type 2 (secondary screen).

Under Assign Secondary Screens, check whether screen 91 of screen sequence SP is assigned to the additional screens. This is the case if a number is entered in the Additional column. If no number is entered, you must assign the screen to the additional screens. To do this, click the "page" icon.

Assign a screen sequence to a combination of one or more transactions, users, material types, or industry sectors. As a result, this screen sequence appears automatically for the respective user(s) when the transaction, material type, or industry sector is chosen

The IMG Node - "Set Up Specification Assignment in material Master " under Specificaiton Master - Basic Data tools shows more information on this activity.

Thanks

Jayakumar