Quality inspection Time in pp/ds

itsgzc
Explorer
0 Kudos
338

Hi everyone,

Here I've struggling with a challenge. My project about the process type manufacturing but I can't not transferring or see the 1 day inspection day in planning board. Normally in MRP2 an d advanced planning view I I set the material input processing time to be 1 day. For that problem I shouldn't create a new workplace for quality.

what should I do? in fact, the material has to wait a day before starting the new operation.

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar
Active Contributor
0 Kudos

Hello,

You have to map it as an operation or you can use wait time between the operations in routing or recipe.

Best Regards,

R.Brahmankar